Week in Review
- Crews completed underground utilities from Adams St. to Jackson St.
- Roadway building began from Adams St. heading west
Two Week Outlook
- Crews will begin installing sanitary sewer from Jackson St. to Oshkosh St.
- Patten St. will be closed between Jackson and Oshkosh until this phase of construction is complete. No vehicle access will be possible. Please contact the Ayres Project Team if you require special accommodations regarding access.